Installing Or Replacing An Expansion Canister: 2076-92F - IBM Storwize V7000 Gen2+ Quick Installation Manual

Table of Contents

Advertisement

Installing or replacing an expansion canister: 2076-92F

You can reinstall an expansion canister in a 2076-92F expansion enclosure or
replace a faulty expansion canister with one from FRU stock.
Before you begin
Important: You can replace an expansion canister without powering off the
expansion enclosure. However, to maintain operating temperature, replace the
expansion canister within 10 minutes of its removal. When an expansion canister is
removed, the reduction in airflow through the enclosure might cause the enclosure
or its components to shut down to protect from overheating.
About this task
An expansion canister provides SAS connectivity between the 2076-92F expansion
enclosure and Storwize V7000 system. The expansion enclosure contains two
expansion canisters. Figure 44 shows an example of an expansion canister. If either
of the two expansion canisters has a failure, the other expansion canister assumes
the full I/O load.
1
2
3
Figure 44. Expansion canister
Procedure
1. Disconnect the elbow of the lower cable management arm to swing it out of the
2. Carefully align the expansion canister with the expansion enclosure.
3. Rotate both the handles outward and insert the expansion canister into the
4. When the expansion canister is fully inserted, rotate each handle inward to lock
54
Storwize V7000 Gen2 and Gen2+: Quick Installation Guide
4
5
6
1 Canister fault indicator
2 Canister status
3 Canister power indicator
4 and 6 SAS link fault indicators
5 and 7 SAS link operational indicators
8 Canister release handles
way, as shown in Figure 45 on page 55.
Follow the procedure that is described in "Moving the cable management
arms" on page 58.
expansion enclosure.
it into position, as shown in Figure 45 on page 55.