Parameter reference (LUI)
9.2 Setup (2.)
Peak 5 End Time (2.7.2.2.12.)
Sets the end time of the high energy cost period 5.
Values
Used in conjunction with Peak 5 Start Time (2.7.2.2.11.) (Page 195) to define the high cost
period.
Peak ON Setpoint Pump 1 (2.7.2.2.13.)
Sets the process point at which Pump 1 will turn on when in a peak period.
Values
To allow the level to go beyond the normal Relay ON Setpoint before a pump is started, enter
the value to be used for the high-energy cost period.
Peak OFF Setpoint Pump 1 (2.7.2.2.14.)
Sets the process point at which Pump 1 will turn off when in a peak period.
To stop the pump(s) before the normal relay OFF Setpoint and reduce pump-running time.
Enter the value to be used for the high cost period.
Peak ON Setpoint Pump 2 (2.7.2.2.15.)
Sets the process point at which Pump 2 will turn on when in a peak period.
Values
To allow the level to go beyond the normal Relay ON Setpoint before a pump is started, enter
the value to be used for the high-energy cost period.
Peak OFF Setpoint Pump 2 (2.7.2.2.16.)
Sets the process point at which Pump 2 will turn off when in a peak period.
Values
To stop the pump(s) before the normal relay OFF Setpoint and reduce pump-running time.
Enter the value to be used for the high cost period.
196
Range: 00:00 to 23:59
Format: HH:MM (24 hour format, for example: for 5:30pm, set parameter to 17:30)
Default: 00:00
Values
Range: 0.000 to 99999.000
Default: 0.000
Range: 0.000 to 99999.000
Default: 0.000
Range: 0.000 to 99999.000
Default: 0.000
Range: 0.000 to 99999.000
Default: 0.000
Operating Instructions, 04/2021, A5E33329501-AG