Commissioning (software)
2.1
General commissioning information
General commissioning information
The inverter can be adapted to various applications by changing the parameter values.
The parameter values can be changed, using one of the following optional components:
• The OP (Operator Panel), plugged into the Option port of the Control Unit
• The STARTER (Commissioning software via PC) can be connected to the Option port
• The MMC for downloading complete parameter sets
This section shows how the commissioning of a G120 Inverter is performed using an OP.
The commissioning process using STARTER is driven by dialog boxes and will not be
described in this manual.
The inverter is delivered with identical factory settings for all CU240S control unit; except the
settings of command and setpoint source and values depending on the power module.
Note
Upload and download
• Upload means to save the parameters from the EEPROM of an inverter to a PC (via
• Download means to write a parameter set held on a PC, MMC or an OP to the RAM or
Control Units CU240S
Operating Instructions (Compact), 04/2006, A5E00766042B AA
using a PC connection Kit
STARTER), MMC or an OP.
EEPROM of an inverter.
2
2-1