Series Commissioning - Siemens SINAMICS G120 Operating Instructions Manual

Hide thumbs Also See for SINAMICS G120:
Table of Contents

Advertisement

Finishing the application setting
Parameter
Description (Parameter name and factory setting (if not variable) in bold)
P0971 = 1
Transfer data from RAM to EEPROM
0: Disabled
1: Start data transfer, RAM → EEPROM
All of the parameter changes are transferred from the RAM into the EEPROM which means
that they are saved in a non-volatile state within the Inverter (data is not lost when the power
fails).
While the transfer is active, "bUSY" will be displayed on the OP. Once the transfer is
completed P0970 will be set internally to "0" and the "P0970" will be displayed.
Note: Data transfer RAM → EEPROM is not necesarry when the commissioning is performed
via the OP, because all parameter settings are stored in EEPROM immediately when changed
by the OP.
5.7.4

Series Commissioning

Overview
Series commissioning means the possibility to transfer the parameter set from one inverter
into a number of other inverters which allows fast commissioning for identical applications
(for example series machines or group inverters).
The series commissioning is divided into the following steps:
● create a valid parameter set
● upload this parameter set
● download of the uploaded parameter set into the new inverter
To perform series commissioning an appropriate parameter set must be available. This
parameter set can be created by parameterizing an Inverter via OP or STARTER.
Control Units CU240S
Operating Instructions, 11/2006, A5E00766042B AA
Commissioning (software)
5.7 Commissioning modes