Commissioning
5.5 Commissioning with STARTER
5.5.2

Adapting the USB interface

Switch on the converter supply voltage and start the STARTER commissioning software.
If you are using STARTER for the first time, you must check whether the USB interface is
correctly set. To do this, click in STARTER on
the procedure if no settings are required. In case 2, a description is provided on how you can
adapt the interface.
Case 1: USB interface OK - no setting is required
If the interface is correctly set, the following screen form shows the converter, which is
directly connected to your computer via the USB interface.
Close this screen form, without selecting the converter(s) that has/have been found. Now
create your STARTER project.
Case 2: USB interface must be set
In this case, the message box "no other nodes found" is displayed. Close the window, and
make the following settings in the "Accessible nodes" screen:
Close this screen form, without selecting the converter(s) that has/have been found. Now
create your STARTER project.
62
Under "Access point activate "DEVICE (STARTER, Scout)"
Under " PG/PC" select "S7USB"
Then click on "Update"
(accessible participants). Case 1 shows