Commissioning
5.1
Commissioning guidelines
Procedure
Proceed as follows to commission the inverter:
1. Define the requirements of
2. Reset the inverter when
3. Check whether the factory
4. Check whether you need to
5. If necessary, adapt the
6. If necessary, set further
7. Save your settings.
You have commissioned the inverter.
Inverter with CU230P-2 Control Units
Operating Instructions, 11/2013, FW V4.6.6, A5E02430659B AG
your application placed on
the drive.
→ (Page 74).
required to the factory
setting.
→ (Page 79).
setting of the inverter is
appropriate for your
application.
If not, start with the basic
commissioning.
→ (Page 80).
adapt the functions of the
terminal strip that you
specify in the basic
commissioning.
→ (Page 93).
communications interface in
the inverter.
→ (Page 107).
functions in the inverter.
→ (Page 225).
→ (Page 323).
5